Outstanding workmanship integrated with quality concrete yields a professional result achieved time and time again by Southern N.H. Concrete Construction.

377,000 Sq/Ft Of Building

Southern NH Concrete supplied and placed 3,200 yards of concrete for walls and footings. In addition to supplying 165 tons of rebar, we installed 390 anchor bolt settings.

63 Days To Complete

Considering the sheer size of this project, Southern NH Concrete was able to easily manage the workload. On average, we placed between 70 yards - 80 yards of concrete daily!

14 Man Crew

The SAFRAN Aerospace Facility was a joint venture with S&S Concrete Floors of New Ipswich, NH. The contractor for this project was Haskell out of Jacksonville, FL