Please send a big thank you to your crew for their work on this project. We installed a 50,000 sq. ft. prefabricated steel building with each column sliding perfectly over your bolts. The steel crew was very impressed. We can’t say how much we appreciate your attention to every detail of the project. Your team is extremely professional and well-trained. Our walls look like glass and they are straight as an arrow.
Dustin Corbett
LEED AP | Windover Construction
0
Sq/Ft Of Building
Southern NH Concrete formed over 450ft of low wall that is 15ft-high and 16in-thick. We placed 16 pilasters that are 6ft x 4ft x 15ft Southern NH Concrete supplied and placed 1,000 yards of concrete, in addition to supplying and installing 65 tons of rebar.
0
Days To Complete
In a little over a month, we were able to use a 60-ton crane to form high walls and set steel. The concrete was pumped by Independent Concrete Pumping.
0
Man Crew
We had 8 men from our crew on form work and 6 men placing rebar. The contractor for the Endicott College Ice Arena was Windover Construction located in Beverly, MA.